It is difficult to distinguish between the time limit for the time limit of the contractor and the time limit. The employer claims that the penalty for overdue period will not be supported.
Release time:
2018-04-27
In actual construction, construction enterprises are likely to have defects such as inadequate preparation for construction, insufficient pre construction capacity and defects in project management. Owners may also have defects such as insufficient payment for project progress, design changes, increased quantities, and unauthorized use without completion and acceptance. At the same time, there may be defects in communication, coordination and coordination between the contracting parties. The above comprehensive reasons, or successively, or overlapping or combined, have resulted in a long delay in the construction period.
In judicial practice, when the contractor sues to the employer for the payment of the project, the employer usually counterclaims, claiming a huge overdue penalty. During the trial, the contractor often only needs to provide the actual completion date and the planned completion date of the contract, which is the number of days of the Contractor's actual delay, that is, the contractor has completed the proof of the delay in the construction period. But in reality, because the Contractor's weak position in the whole construction process, the contractor is often difficult to get a written visa that the contractor agrees to postpone the construction period even if the contractor causes the time limit due to the cause of the contractor. In the course of construction, the contractor usually coax the contractor to speed up the construction progress, oral promise will not be investigated for the duration of the work or the promise of a visa after the end of the project. Once the project is completed, the employer will be held responsible for the delay in the labor contract due to the purpose of deduction, payment of the project and so on. The contractor is often passive because of his lack of evidence and lack of evidence.
In recent years, in view of the increasing number of similar disputes, the high people's Court of Anhui Province, in view of the practice of construction, specially promulgated the Guidance Opinions (two) on the application of legal problems in the case of dispute cases in the construction contract of construction projects in Anhui province (two), Fourth "the contractor can not provide the visa of the delay time." Documents, but can prove that the project has delayed construction, no construction conditions, design changes, increase in the amount of engineering, the delay of completion of subcontracting projects designated by the contractor, and no full payment of the payment of the project, which can not be attributed to the contractor, and the construction schedule may be affected by the contractor. "
In December 21, 2015, the Supreme People's court tried to compensate for the delay of the contractor B in the case of the compensation for the delay of the contractor B. The contractor B had the defects of the project management, the delay of the work period, and the unauthorized withdrawal of the field. It is difficult to distinguish between the two parties' liability for overdue period after acceptance and acceptance. In this case, the Supreme People's court holds that it is obvious that it is contrary to the principle of fairness that the contractor B should bear the liability for breach of contract unilaterally without distinguishing the size of the breach of contract and the amount of the loss. (Wang Furong)
Recommended news
2026-11-11
In early November, the Group successfully passed the on-site verification for the administrative license renewal of its biennial comprehensive working-hour system, completing the new approval process. This has further standardized workforce management, reinforced compliance safeguards, balanced corporate development with employee rights, and strengthened employment security to support the Group’s resilient and sustainable growth.
2026-11-03
On the afternoon of November 2, Qidong City held the second session of its 2026 Entrepreneurs’ Symposium. Cao Yanhui, Secretary of the Municipal Party Committee, attended and addressed the meeting; Qin Guangrong, Deputy Secretary of the Municipal Party Committee and Mayor, presided over the event; and municipal leaders Wang Yubing, Guo Jian, Song Haihua, among others, also took part.
2026-11-03
The Group has been awarded two provincial-level construction methods in the Tibet Autonomous Region.
At the end of October, the Construction Industry Association of the Tibet Autonomous Region announced the list of regional-level construction methods for 2026. Two methods submitted by the Group—“Construction Method for Temporary Site Drainage Channels Using Prefabricated Polymer Materials” and “Spatial Dimension Measurement Method for Unit Acceptance Based on Total Stations”—were successfully selected.
2026-10-27
Two projects of the Group have been awarded the Urumqi and Bazhou Quality Engineering Awards.
In mid-October, two Xinjiang projects under the Group were successively awarded the “2026 Urumqi Quality Project” and the “2026 Bazhou Quality Project,” reflecting the high recognition from the local industry authorities in both regions for the projects’ construction quality, safety management, and civilized site practices.
2026-10-19
Recently, two QC achievements submitted by the Group—“Improving the First‑Pass Yield of Concrete Surface Finishing” (Maosheng International Engineering Branch) and “Enhancing Sound Insulation and Noise Reduction in Serviced Apartment Rooms” (Jinrun Branch)—were recognized as Class I awards at the 2026 Shanghai Municipal Engineering Construction QC Group Awards.
2026-10-19
On the Double Ninth Festival, hearts are warmed by the golden autumn. As this cherished occasion approaches, the Trade Union of Jiangsu Qian’an Construction Group organized a care‑giving visit for its senior employees, paying special visits to retired staff aged eighty and above to extend festive greetings and heartfelt wishes.