集团大丰港数智产业350MW新型渔光一体化项目建设迎寒攻坚
Release time:
2026-01-25
集团大丰港数智产业350MW新型渔光一体化项目建设迎寒攻坚
隆冬时节的苏北大地,寒风凛冽、冰天雪地。近百名启安人依旧坚守在大丰港数智产业350MW新型渔光一体化项目施工现场,傲霜斗寒、全力以赴推进项目建设。

大丰港数智产业350MW新型渔光一体化项目位于江苏省盐城市大丰港盐碱滩涂上,占地超4000亩,共计166只塘,需用PHC桩约20万米,钢材约2.5万吨,715Wp(N型)单晶硅双面双玻组件约57万块。项目由集团金和光电分公司开发建设,施工内容包含场地平整、塘埂改造、桩基作业、钢梁及檩条等吊装、逆变器和箱变安装、高低压电缆敷设和一座220KV升压站,预计总投资超10亿元,建成后年发电量44702.1万kWh。

与传统光伏电站不同,该项目创新性地将新能源发电与精品渔业养殖高效结合,实现了“板上绿色发电,板下水产养殖”的立体复合利用,成为当地推动绿色能源与现代农业融合发展的重点示范工程,更是被上级部门确定为2026年省级春季预定重大观摩活动展示项目,责任重大、使命光荣!

目前,项目部已高质量完成13个样板区的1.5万多米桩基工程、展示区基础和两个样板区的钢结构工程,有能力确保在三月份圆满建成高标准、可观摩的样板工程和展示区,为集团公司在新能源领域再添一座标杆工程。(金和光电分公司)
Recommended news
2026-09-18
In mid-September, a foreign‑owned owner‑audit expert team from Jotun’s Norwegian headquarters conducted a three‑day, headquarter‑level specialized safety audit at the Jotun Zhangjiagang project site undertaken by the Group.
2026-09-18
The Roche (Shanghai) project of the Group has successfully achieved 2 million safe man-hours.
On September 17, the Roche (Shanghai) Biopharmaceutical Production Base project, undertaken by the Group, successfully reached the milestone of 2 million safe man-hours.
2026-09-18
On September 16–17, the China Chemical Construction Enterprises Association held a training course on building “Quality‑Trusted Work Teams” in Chengdu, with representatives from the Group in attendance. The training featured a live lecture by Shi Jie, a senior expert of the Association.
2026-09-09
Good News Abounds | The Group Has Secured Multiple Emerging Industry Projects in Succession
In the golden autumn season, bountiful harvests abound, and new‑generation growth sectors showcase their strength. Since August, leveraging its deep-rooted expertise and core competencies in industrial installation, the Group has successively won bids for five key projects in emerging productivity fields, with a total contract value exceeding RMB 250 million, injecting robust momentum into its resilient year‑end performance.
2026-09-03
Recently, the China Construction Industry Association announced the results of the 2026 Engineering Construction Quality Management Team Achievement Competition. Two QC projects submitted by the Group—“Improving the First-Pass Acceptance Rate for One-Time Forming of Exterior Concrete Moldings” and “Enhancing the First-Pass Welding Acceptance Rate for Dissimilar Steels”—were awarded second and third prizes, respectively.
2026-09-01
On the afternoon of August 31, the Group convened a meeting of heads of regional companies and departmental offices in the fourth-floor conference room at its headquarters to deliberate on the implementation of the spirit of the symposium for branch‑office representatives held by the Group on August 30.