Shaanqi Heavy Truck and Cummins Project (Mechanical and Electrical Installation) Construction Experience Sharing


1. After winning the bid for the project, the electrical construction workers should deepen the drawings and not blindly follow the direction of the drawings; The specifications and sizes of cables and cable trays shall be improved to meet the use standards and specifications.

2. During the bridge construction, it was found that the three-way reducing elbow of the bridge was purchased as finished parts. It is suggested to cancel the supply of finished products for the next project and let the construction team make them according to the actual situation on site.

3. The piping of the air conditioner valve group in the general assembly workshop is fabricated and installed on site. It is suggested that the next project can be prefabricated in the processing plant, and only needs to be bolted to the site.

4. On the site of electrical lighting piping in the general assembly workshop, the piping shall be completed before threading. It is suggested that piping and threading can be carried out simultaneously in the next project to save manpower and material resources.

5. All pumps and valve groups in the complex station can be prefabricated in the processing yard, and only need to be installed on site.

6. Too little glue was brushed during the thermal insulation construction in the general assembly workshop, which resulted in internal water accumulation due to long-term temperature difference. It is suggested to carry out relevant work disclosure before the construction of the next project.

7. The wages of subcontracting teams must be paid first to the workers and then to the subcontracting boss.

8. In terms of the use of machinery, it is recommended to calculate the machinery cost and send it to the subcontracting teams for their own control to avoid waste in the use of machinery.

9. For threaded copper valves below DN50, special open-end wrenches must be used, and pipe wrenches and other tools are not allowed.

10. Specify some construction details in advance, such as the scope of finished tee of welded steel pipe, the connection mode of pipe, the type of support, etc. It is better to set a sample section in advance to avoid material and labor losses.

11. Before the installation of the pipe support, the spacing of the pipe and the reducing position of the pipe must be clear to avoid the drilling of the support in the later period.

12. The biggest impact on future projects: modular hoisting shall be adopted as far as possible, and the site shall be easy to process and assemble. See the attached figure for details.

Recommended news


The Group’s Roche Pharmaceutical Project has been awarded the One-Million-Safety-Hours Award.

On June 5, the Roche (Shanghai) Biopharmaceutical Production Base Project (Phase I) held a ceremony to celebrate reaching one million safe man-hours, and the Group was presented with a commemorative trophy.


The Group convened a special meeting of the dedicated task force for major project services.

On the afternoon of May 25, the Group convened a special working meeting on major project services in the 16th-floor conference room, with senior management and all members of the Major Project Management Department in attendance. The meeting was chaired by Zhang Jian, General Manager of the Group.


The Jinshun Branch of the Group organized a project management observation and exchange event.

On May 23, the Jinshun Branch of the Group organized an on-site observation and exchange session on project management. All project managers, frontline supervisors, and relevant personnel from various functional departments of the branch attended the event, while selected managers from China State Construction Engineering Corporation Third Bureau and Xinjiang Production and Construction Corps Construction Engineering Company were invited to participate in the observation and discussion.


Group General Manager Zhang Jian Visits Asahi Kasei (Nantong) to Deepen Cooperation and Exchange

On May 8, Zhang Jian, General Manager of the Group, led a delegation to Asahi Kasei Fine Chemicals (Nantong) Co., Ltd. for a project follow-up visit and exchange meeting, during which they held a symposium with Asahi Kasei General Manager Yuichi Sanro and other senior executives. Cai Ting and Gao Mingmin, Deputy General Managers of the Group, also attended the event.


The Group has won the bid for the Fujian Yuanfu Technology project to produce 3,000 tons per year of high-purity lithium fluoride.

Recently, good news emerged from the southern market: the Group has successfully won the bid for Fujian Yuanfu Technology Co., Ltd.’s 3,000-ton-per-year high-purity lithium fluoride project under an EPC general contracting model, with a total contract value exceeding RMB 40 million.


The Shanghai Wangyuan Building Hotel’s comprehensive renovation project has entered its final sprint.

In mid-May, the hotel renovation project for the Shanghai Wangyuan Building, undertaken by the Group, entered its final, critical phase of intensive completion. At present, all core construction tasks— including the main interior finishing works and the installation and commissioning of various mechanical and electrical systems—have been successfully completed. The project’s focus has now fully shifted to meticulous fine‑tuning, integrated system testing and commissioning, and comprehensive on‑site cleanup and final finishing.