Shaanqi Heavy Truck and Cummins Project (Mechanical and Electrical Installation) Construction Experience Sharing


1. After winning the bid for the project, the electrical construction workers should deepen the drawings and not blindly follow the direction of the drawings; The specifications and sizes of cables and cable trays shall be improved to meet the use standards and specifications.

2. During the bridge construction, it was found that the three-way reducing elbow of the bridge was purchased as finished parts. It is suggested to cancel the supply of finished products for the next project and let the construction team make them according to the actual situation on site.

3. The piping of the air conditioner valve group in the general assembly workshop is fabricated and installed on site. It is suggested that the next project can be prefabricated in the processing plant, and only needs to be bolted to the site.

4. On the site of electrical lighting piping in the general assembly workshop, the piping shall be completed before threading. It is suggested that piping and threading can be carried out simultaneously in the next project to save manpower and material resources.

5. All pumps and valve groups in the complex station can be prefabricated in the processing yard, and only need to be installed on site.

6. Too little glue was brushed during the thermal insulation construction in the general assembly workshop, which resulted in internal water accumulation due to long-term temperature difference. It is suggested to carry out relevant work disclosure before the construction of the next project.

7. The wages of subcontracting teams must be paid first to the workers and then to the subcontracting boss.

8. In terms of the use of machinery, it is recommended to calculate the machinery cost and send it to the subcontracting teams for their own control to avoid waste in the use of machinery.

9. For threaded copper valves below DN50, special open-end wrenches must be used, and pipe wrenches and other tools are not allowed.

10. Specify some construction details in advance, such as the scope of finished tee of welded steel pipe, the connection mode of pipe, the type of support, etc. It is better to set a sample section in advance to avoid material and labor losses.

11. Before the installation of the pipe support, the spacing of the pipe and the reducing position of the pipe must be clear to avoid the drilling of the support in the later period.

12. The biggest impact on future projects: modular hoisting shall be adopted as far as possible, and the site shall be easy to process and assemble. See the attached figure for details.

Recommended news


Two QC achievements of the Group have been awarded as First-Class Awards in Shanghai’s engineering construction sector.

Recently, two QC achievements submitted by the Group—“Improving the First‑Pass Yield of Concrete Surface Finishing” (Maosheng International Engineering Branch) and “Enhancing Sound Insulation and Noise Reduction in Serviced Apartment Rooms” (Jinrun Branch)—were recognized as Class I awards at the 2026 Shanghai Municipal Engineering Construction QC Group Awards.


Respecting the Elderly on Double Ninth Festival Warms the Heart; Qian’an’s Warmth and Compassion Passes on the Flame of Kindness

On the Double Ninth Festival, hearts are warmed by the golden autumn. As this cherished occasion approaches, the Trade Union of Jiangsu Qian’an Construction Group organized a care‑giving visit for its senior employees, paying special visits to retired staff aged eighty and above to extend festive greetings and heartfelt wishes.


The Group was awarded ExxonMobil’s “Outstanding Construction Enterprise” title.

Recently, the Group received an “Outstanding Construction Enterprise” certificate from ExxonMobil, a global energy and chemical industry giant, in recognition of the project team for the Daya Bay R&D Center laboratory expansion project for its exemplary implementation of the “Win-Win Cooperation—Zero Injuries” philosophy throughout the construction process.


Zhang Hua, Chairman of Zhejiang Second Construction Group, and his delegation visited the Group for exchanges and study.

On October 8, Zhang Hua, Secretary of the Party Committee and Chairman of Zhejiang Second Construction Group, led a core management team to visit the Group for an exchange and study session. Yin Weidong, Secretary of the Party Committee and Chairman of the Group, General Manager Zhang Jian, Deputy General Manager Xu Hao, and other senior executives attended the event.


The Group dispatched representatives to attend the Exchange Meeting on Construction Project Quality and Safety Management and the On-site Observation Session.

In late September, the China Construction Enterprise Management Association organized an experience-sharing and on-site observation conference on quality and safety management in construction projects in Guangzhou, which was attended by representatives from the Group.


Empowering Communities Through Health: Experts Bring Science-Based Education to Qian’an

On September 18, Jiangsu Qian’an Construction Group, in collaboration with the Science Education Base of Qidong People’s Hospital, hosted the 2026 National Science Popularization Event.