Shaanqi Heavy Truck and Cummins Project (Mechanical and Electrical Installation) Construction Experience Sharing
Release time:
2022-12-06


1. After winning the bid for the project, the electrical construction workers should deepen the drawings and not blindly follow the direction of the drawings; The specifications and sizes of cables and cable trays shall be improved to meet the use standards and specifications.
2. During the bridge construction, it was found that the three-way reducing elbow of the bridge was purchased as finished parts. It is suggested to cancel the supply of finished products for the next project and let the construction team make them according to the actual situation on site.
3. The piping of the air conditioner valve group in the general assembly workshop is fabricated and installed on site. It is suggested that the next project can be prefabricated in the processing plant, and only needs to be bolted to the site.
4. On the site of electrical lighting piping in the general assembly workshop, the piping shall be completed before threading. It is suggested that piping and threading can be carried out simultaneously in the next project to save manpower and material resources.
5. All pumps and valve groups in the complex station can be prefabricated in the processing yard, and only need to be installed on site.
6. Too little glue was brushed during the thermal insulation construction in the general assembly workshop, which resulted in internal water accumulation due to long-term temperature difference. It is suggested to carry out relevant work disclosure before the construction of the next project.
7. The wages of subcontracting teams must be paid first to the workers and then to the subcontracting boss.
8. In terms of the use of machinery, it is recommended to calculate the machinery cost and send it to the subcontracting teams for their own control to avoid waste in the use of machinery.
9. For threaded copper valves below DN50, special open-end wrenches must be used, and pipe wrenches and other tools are not allowed.
10. Specify some construction details in advance, such as the scope of finished tee of welded steel pipe, the connection mode of pipe, the type of support, etc. It is better to set a sample section in advance to avoid material and labor losses.
11. Before the installation of the pipe support, the spacing of the pipe and the reducing position of the pipe must be clear to avoid the drilling of the support in the later period.
12. The biggest impact on future projects: modular hoisting shall be adopted as far as possible, and the site shall be easy to process and assemble. See the attached figure for details.


Recommended news
2026-09-18
In mid-September, a foreign‑owned owner‑audit expert team from Jotun’s Norwegian headquarters conducted a three‑day, headquarter‑level specialized safety audit at the Jotun Zhangjiagang project site undertaken by the Group.
2026-09-18
The Roche (Shanghai) project of the Group has successfully achieved 2 million safe man-hours.
On September 17, the Roche (Shanghai) Biopharmaceutical Production Base project, undertaken by the Group, successfully reached the milestone of 2 million safe man-hours.
2026-09-18
On September 16–17, the China Chemical Construction Enterprises Association held a training course on building “Quality‑Trusted Work Teams” in Chengdu, with representatives from the Group in attendance. The training featured a live lecture by Shi Jie, a senior expert of the Association.
2026-09-09
Good News Abounds | The Group Has Secured Multiple Emerging Industry Projects in Succession
In the golden autumn season, bountiful harvests abound, and new‑generation growth sectors showcase their strength. Since August, leveraging its deep-rooted expertise and core competencies in industrial installation, the Group has successively won bids for five key projects in emerging productivity fields, with a total contract value exceeding RMB 250 million, injecting robust momentum into its resilient year‑end performance.
2026-09-03
Recently, the China Construction Industry Association announced the results of the 2026 Engineering Construction Quality Management Team Achievement Competition. Two QC projects submitted by the Group—“Improving the First-Pass Acceptance Rate for One-Time Forming of Exterior Concrete Moldings” and “Enhancing the First-Pass Welding Acceptance Rate for Dissimilar Steels”—were awarded second and third prizes, respectively.
2026-09-01
On the afternoon of August 31, the Group convened a meeting of heads of regional companies and departmental offices in the fourth-floor conference room at its headquarters to deliberate on the implementation of the spirit of the symposium for branch‑office representatives held by the Group on August 30.