Health post station project duty diary


Health post station project duty diary

On the evening of Friday, April 8, the moon is bright and the stars are sparse

The construction site is as bright as day, and the red flag of the "vanguard of Party members" at the gate is hunting. The main work tonight is the pouring of the bottom plate of the rainwater collection tank, the pouring of the top plate of the garbage room, the excavation of the sewage tank and the precipitation at the bottom.

The personnel on duty of the project have been patrolling the construction site. The lighting on the site is sufficient, the bottom plate of the rainwater collection tank has been poured, and the dewatering pump on the side works well; The foundation pit of sewage tank is being excavated; About 30 people were binding reinforcement on the roof slab of the garbage house, and the support bent was checked. There was a lack of sweeping rod, cross bar and inclined support. The woodworking team was immediately required to make rectification.

20: 00, a worker wearing a hard hat and a pair of rubber shoes walked past the gate of the construction site, swearing: "I have been working since 11:00 noon, and I can't eat meals (there's no boxed lunch). I've worked overtime with a hammer, and I quit!"

20: 30. The pouring of the bottom plate of the rainwater pool is completed. The reinforcement bent of the carpentry team in the garbage room has been connected, and the sweeping rod, cross bar and cross bridging have been set in place. After work, the carpentry team chatted with them all the way to the parking point and learned that they all lived in Hefeng and JuYang. Due to the epidemic control, they walked more than ten miles from the "five head water leak (place name)", got home at 2:30 a.m. and arrived at the construction site at 6:30 a.m. Four night shifts have been added in a row.

"How about overtime pay?"

"I didn't ask. The project is important. Grab the work first."

"Can you bear it?"

"OK."

I nodded and told them to be careful on the way.

At 21:30, the garbage room was ready to cast the roof, and the support bent was checked and accepted together with the supervisor. I saw that the abusive worker was on site again.

"Have you eaten?"

"No, after eating a bucket of instant noodles, put a cushion first, and the lunch box boss went to get it."

"Didn't you stop working overtime today?" Asked half jokingly.

"That's angry. I can't work overtime. The project is so tight that it will affect the one-day construction period. I can distinguish the severity."

Just then, the boss took more than 10 boxed meals and asked the workers to eat. It turned out that in order to grab the top plate reinforcement binding, more than 10 reinforcement workers came at night, and there were fewer boxed meals.

At 22:00, the carpenter began to cast the concrete carefully and carefully. When the pouring was almost finished, he came down from the shelf and I went to his side.

"Why did you come back from work?"

"As soon as I ran to the door, the boss called me and asked me to help. He said that I lived at the small gate. I was closest to the project. I worked hard and left to see the mold. I moved the faucet and came back. Life must fall first." The voice is obviously a little hoarse

I wanted to take a picture of him to record the ordinary people's feelings. When I went back to him, the foreman told me that he had just left. I think today's nodes are all robbed. He can get up later and have a good sleep tomorrow.

At 22:30, the excavation of the sewage tank was coming to an end, and the workers on the edge were preparing for the precipitation.

"When did you come?"

"It will arrive at 8 o'clock."

"I've been waiting for three hours."

"No way, we can't finish it today, and we can't pour the bottom plate tomorrow, which will affect the construction period."

At 23:00, the excavator master took the initiative to chat with me after getting off the machine. His eyes were a little puffy and lacked sleep.

"Have you been working overtime for a long time?"

"Night shift for a week in a row."

"Go back to bed early today."

"I live in Xingang town. There is still more than an hour on the road. It is estimated that it will be 1 o'clock when I get home."

At 23:30, the dewatering cannula was completed, the pump began to operate and pumped out, and the electrician on duty patrolled the site.

"Are you on the night shift today?"

"It's a."

"When is it worth?"

"Dawn."

"Get it?"

"Ensure the normal operation of the dewatering pump and check it once an hour."

At the moment of fighting against the epidemic, pay tribute to everyone who silently pays for the Qidong health post station (peacetime and wartime combination) project. I wish the mountains and rivers are safe and the country is peaceful and the people are safe! (Lu Jianjian)

Recommended news


The Kuaike Haofudun project, undertaken by the Group, has officially entered production, and General Manager Zhang Jian was invited to attend the opening ceremony.

On the morning of June 25, the grand opening ceremony of Quake Haofudun Materials Technology (Suzhou) Co., Ltd. was held in the Zhangjiagang Free Trade Zone. Zhang Jian, General Manager of the Group, along with Deputy General Manager Shi Saicai and other invited guests, attended the event and jointly witnessed this significant milestone marking the project’s entry into production.


The Group achieved excellent results in the preliminary round of the province-wide construction safety production knowledge competition.

Recently, the preliminary-round results of the province-wide construction‑site safety production knowledge competition were officially announced. The Group achieved an outstanding team performance, with six participants ranking in the top ten, placing first among all construction enterprises in the province.


The Group’s Roche Pharmaceutical project employs air‑suspended air cushions to achieve non‑destructive construction.

In mid-June, the Roche Pharmaceuticals project, constructed by the Group’s Maosheng International Engineering Branch, successfully completed the indoor relocation of three 13-ton heavy-duty pieces of equipment within a high‑standard epoxy flooring area, utilizing an air‑suspension cushion‑lifting technique.


Carrying forward the glory of military service, we uphold our spirit of dedication to peace and security.

On June 2, the “Carrying Forward the Glory of Military Service, Ensuring the Well-being of Veteran Soldiers” Care Foundation was officially established at the Qidong Municipal Bureau of Veterans Affairs and the Municipal Charity Federation, under the leadership of Gong Shancong, Deputy General Manager of the Group. The foundation aims to “show care for veterans, alleviate their difficulties, safeguard their health and well-being, and spread warmth throughout society.”


The Group’s Roche Pharmaceutical Project has been awarded the One-Million-Safety-Hours Award.

On June 5, the Roche (Shanghai) Biopharmaceutical Production Base Project (Phase I) held a ceremony to celebrate reaching one million safe man-hours, and the Group was presented with a commemorative trophy.


The Group convened a special meeting of the dedicated task force for major project services.

On the afternoon of May 25, the Group convened a special working meeting on major project services in the 16th-floor conference room, with senior management and all members of the Major Project Management Department in attendance. The meeting was chaired by Zhang Jian, General Manager of the Group.